Through a partnership sealed in February 2022, Globe and Converge embarked on its first joint project in 2022: a co-build spanning 137 kilometers from Pili, Camarines Sur, to Legazpi City, Albay. Utilizing cutting-edge technology, this venture includes the deployment of state-of-the-art microduct solution underground facilities. This project wrapped up in Q3 of 2022.
Following the success of the initial undertaking, a second co-build project in Leyte Province began in the third quarter of 2023. Spanning 209 kilometers to connect Tacloban and Maasin via Baybay, it is currently 80% complete and is expected to conclude by the third quarter of 2024.